Prev Question
Next Question

Due to changes in IT, the disaster recovery plan of a large organization has been changed. What
is the PRIMARY risk if the new plan is not tested?

A.
Catastrophic service interruption

B.
High consumption of resources

C.
Total cost of the recovery may not be minimized

D.
Users and recovery teams may face severe difficulties when activating the plan

Explanation:
Choices B, C and D are all possible problems that might occur, and would cause difficulties and
financial losses or waste of resources. However, if a new disaster recovery plan is not tested, the
possibility of a catastrophic service interruption is the most critical of all risks.

Prev Question
Next Question
Tagged:

Leave a Reply

Your email address will not be published. Required fields are marked *