What should you do?

You need to ensure that you can view only the tasks on your projects critical path. What should you do? A.On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box. B.View the projects Gantt chart and apply the Critical group. C.View the project’s Gantt chart and apply the […]

Read More

What should you do?

You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do? A.Use the Resource Name column drop-down list. B.Use the Resource Pool feature. C.Use the Team Planner feature. D.Use the Level Selected feature. Show […]

Read More

What should you do?

Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do? A.Create cost tables to include rates that activate on effective dates. B.Change the resource availability settings to establish Units for selected dates. C.Create resources that include fixed Standard […]

Read More

What should you do?

You have team members who work on one of the following shifts: Monday through Friday: 8 hours a day. Tuesday through Saturday: 10 hours a day. Sunday through Wednesday: 12 hours a day. You need to ensure that your project plan accommodates the different shifts. What should you do? A.Create shift resource departments. B.Change the […]

Read More

Which two actions should you perform?

Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today’s data. Which two actions should you perform? Each correct answer presents part of the solution. A.From the […]

Read More

What should you do?

You need to ensure that you can view only the tasks on your projects critical path. What should you do? A.On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box. B.View the projects Gantt chart and apply the Critical group. C.View the project’s Gantt chart and apply the […]

Read More

Which command should you use?

You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use? A.Outdent B.Fill Down C.Insert Summary D.Move Task Show Answer

Read More

What should you do?

The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do? A.Select the Project Summary Task option. B.Select the Summary Tasks option. C.Create […]

Read More

What should you do?

You need to replace the resource assignment for an in-progress task. You also need to retain the Work, Actual Work, Remaining Work, and Baseline data for the task. What should you do? A.Use the Resource Name column drop-down list. B.Use the Resource Pool feature. C.Use the Team Planner feature. D.Use the Level Selected feature. Show […]

Read More

Which set of values describes the specified task?

Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50 percent on the task. You change Johns assignment units to 50 percent for the […]

Read More