How can you view the available resources within the next 30 days to plan on task assignment based on resource

You are a project manager in your organization. You have several activities that need to becompleted within the next thirty days for your project to reach its deadline on time. How can youview the available resources within the next 30 days to plan on task assignment based on resourceavailability? A. View the available resources through …

Which one of the following is NOT a site group that is created automatically?

Project Server automatically creates four site groups within the project workspace. Which one of thefollowing is NOT a site group that is created automatically? A. Readers B. Web administrators C. Project managers D. Stakeholders Explanation: There is no such site group as stakeholders within the project workspace by default. The four groupsthat are created automatically …

you need to include in your RESTORE DATABASE tatement to restore the full database backup that comes before th

You are the Microsoft Project Server administrator for your organization and you need to perform arestore to the PSGHT SQL database. You have been using the differential model so you will need torestore from multiple media. What clause will you need to include in your RESTORE DATABASEtatement to restore the full database backup that comes …

How will you accomplish the task?

You work as a Project Manager for company.com Inc. You would like to create a filter in order toview all the jobs submitted to the queue within the last seven days. How will you accomplish thetask? A. This task is possible; you should use the filter “All jobs in the past week” through Project Web …

How can you change the Site Theme?

You would like to change the Site Theme of your project workspace. How can you change the SiteTheme? A. Choose Site Actions, and then select Site Settings. B. Choose Site Settings, and then select Customize. C. Choose Site Customization, and then select Site Settings. D. Choose Site Details, and then select Options. Explanation:Through the workspace …

What command should Gary use?

Gary is the Microsoft Project Server administrator for his company, and is configuring a restoremethod for his SQL Server. Gary would like to use a command to ensure that the backup operationverifies each page for checksum and torn page and for the entire backup. What command shouldGary use? A. STOP_ON_ERROR B. NO_CHECKSUM C. CHECKSUM D. …

Which one of the following is NOT a baseline that can be captured in Microsoft Project Server?

There are three primary baselines in a project. Which one of the following is NOT a baseline that canbe captured in Microsoft Project Server? A. Schedule B. Cost C. Quality D. Scope Explanation:Quality is not a project management baseline. Scope often serves as the quality baseline as itrepresents all that the project should deliver.Answer option …